Learn what a project baseline is, the scope, schedule and cost baselines, how to set one step by step and when to change it.
A project baseline is the approved version of a project’s scope, schedule and cost that all later performance is measured against. It is set once planning is complete and the sponsor has signed off the plan, and it only changes through formal change control. Without a baseline, there is no objective way to say whether a project is on track; with one, every variance can be measured, explained and acted on. This guide explains the three types of baseline, how to set one step by step, how it differs from the project plan, when it should be changed and how to track it in Microsoft Project.
Advance your career with a Professional Project Management Diploma, NFQ Level 8, and IPMA® certification
A project baseline is the formally approved snapshot of the project plan, agreed by the sponsor and key stakeholders before execution begins. It records what the project will deliver, when and at what cost. It answers three questions: what are we delivering, when will it be done and what will it cost?
Every progress report and performance conversation refers back to this reference. Without it, reporting becomes subjective. With it, variances are objective and measurable.
The baseline is not the same as the current plan or a forecast. As the project unfolds, the current plan changes in response to risks, resources and approved changes. The baseline stays fixed, so the team can compare where it is now with where it originally planned to be.
Most project management standards recognise three baselines. Together they form the performance measurement baseline, the integrated reference for performance reporting and earned value analysis.
| Baseline | What it contains | What it helps you control |
|---|---|---|
| Scope baseline | The approved scope statement, work breakdown structure (WBS) and WBS dictionary | What is and is not included, protecting against scope creep |
| Schedule baseline | The approved schedule, with planned start and finish dates for activities and milestones | Delays and their knock-on effect on the critical path |
| Cost baseline | The approved, time-phased budget, often shown as an S-curve of cumulative spend | Spending trends and the forecast final cost |
The scope baseline gives every new request a clear test: is this something we agreed to deliver? Our guide to scope creep explains why that matters. The schedule baseline makes delays visible early, and the cost baseline lets sponsors and finance teams see whether spending matches progress.
Clear baselines also make it easier to manage project deliverables and milestones, because each one has an agreed date and budget to report against.
Only set a baseline once planning is genuinely complete. A baseline set too early is a false reference that will be meaningless within days.
IPM’s Smart Scheduling: Strategic Plans for On-Time Projects course covers schedule development in depth.
Advance your career with project scheduling training. Master scheduling management, prevent delays, and deliver projects on time with IPM.
The two are closely related but not interchangeable, and confusing them causes real governance problems.
| Aspect | Project baseline | Project plan |
|---|---|---|
| Nature | Fixed snapshot of the approved plan | Living document, updated regularly |
| Changes | Only through approved change control | Whenever the team’s thinking or circumstances change |
| Purpose | Reference point for measuring performance | Current guide to how the work will be done |
| Answers | How are we doing against what we promised? | What is the most likely outcome from here? |
A simple analogy: the baseline is the destination and route agreed at the start of a journey. The current plan is the satnav, which recalculates when there is traffic but keeps the same destination. Changing the destination needs a conscious decision by everyone in the car, not a quiet recalculation. Our guide to what a project plan is covers the plan itself.
Construction: a new office building in Dublin has a scope baseline covering the footprint, floors, fit-out specification and landscaping; a schedule baseline running from January to handover in December; and a cost baseline of €4.2 million spread across the year. Midway through, the client asks for an extra floor. That is outside the scope baseline, so the project manager raises a change request. The assessment shows an extra €600,000, six more weeks and a planning amendment. The steering committee approves it, and all three baselines are formally revised, with the originals kept on record.
Software: a CRM migration has a schedule baseline with go-live on 30 June. In April, testing shows two integrations are more complex than expected. The project manager analyses the variance, presents the impact and secures approval for a revised go-live of 31 July. The June baseline is retained, so the full history is visible.
Only through formal change control. If baselines are adjusted informally every time the project drifts, they stop being a measurement tool and simply mirror whatever is happening.
Legitimate reasons for a baseline change include:
The baseline should not be changed just because the project is running late or over budget for reasons within its control. In that case, the right response is recovery action, with the variance reported honestly. A useful rule of thumb: change the baseline when the world has changed, not when the plan has proved difficult. IPM’s Scope Control: Define & Deliver What Matters course covers how to protect scope and baselines in practice.
Microsoft Project has built-in baseline features.
IPM’s Microsoft Project Fundamentals course covers these features hands-on.
The baseline is also the foundation of earned value management (EVM). EVM compares planned value, taken from the time-phased cost baseline, with earned value (the budgeted cost of work actually completed) and actual cost. From these, project managers calculate cost and schedule variances and indices and forecast the final cost and completion date. If the baseline is careless or has been quietly adjusted to hide problems, every EVM figure built on it is unreliable.
Hands-on Microsoft Project training in Ireland. Gain practical skills and an IPM Certificate to prove your capability.
A project baseline is the foundation of every meaningful performance conversation, from the first progress report to the final review. Set it only when planning is complete, get formal approval for scope, schedule and cost together, keep it separate from the living plan and change it only through change control when the world, not the team’s performance, has changed. These are core skills developed in IPM CPM Level 1, which is assessed through training performance and practical assignments rather than a single exam.
Advance your career with a Professional Project Management Diploma, NFQ Level 8, and IPMA® certification
A baseline plan is the formally approved version of the project’s scope, schedule and cost, set before execution begins. It is the fixed reference against which actual performance is compared and only changes through approved change control.
The scope baseline (scope statement, WBS and WBS dictionary), the schedule baseline (approved planned dates) and the cost baseline (approved time-phased budget). Together they form the performance measurement baseline.
Only when a change has been approved through change control, for example a scope change, a major external event or a sponsor decision. It should not be changed just to hide poor performance.
The plan is a living document updated as the project progresses. The baseline is a fixed snapshot of the approved plan, used to measure performance.
Save it from the Project tab using Set Baseline, then use the Tracking Gantt view, or add baseline bars through Bar Styles, to display baseline and current bars side by side.
Highly in-demand across roles, industries, and experience levels
Book Your Free ConsultationJoin IPM Hub, the free community where Project Managers share real challenges and learn from each other.
10% Off your first On-Demand course when you join.
Please activate your account by clicking the verification link we’ve sent to your email.
Once verified, your 10% code will arrive by email.
If the email doesn’t appear soon, please check your spam or junk folder.
We use cookies to ensure you get the best experience of our website. By clicking “Accept”, you consent to our use of cookies.